25th January 2018., representatives of the companies Elektromreža Srbije AD Beograd, Elektromontaža d.o.o. Kraljevo and Energoprojekt Oprema a.d. Beograd, together with a representative of investor HOPS d.o.o. transmission area Osijek, had a tour on part of the 17,6 km long 110 kV transmission line Ernestinovo-Vinkovci, where Dalekovod d.d. perform the installation of the ACCC ® conductor.
The purpose of the visit was to introduce guests to the benefits of the ACCC ® conductors, especially in the reconstruction of the transmission lines, as well as the way of installation of the ACCC ® conductor and the corresponding jointing and suspension equipment.